Categories Roads

Bengaluru-Chennai Expressway Nears Completion: Full Launch Expected August 2025

Union Road Transport Minister Nitin Gadkari has said that the Bengaluru–Chennai Expressway will be opened by Prime Minister Narendra Modi in August 2025.

The Karnataka part of the expressway, which is 71 km long, is almost finished. But a lot of work is still left in the Andhra Pradesh and Tamil Nadu sections.

Completed stretches in Karnataka include:

  • Hoskote to Malur (26.4 km) – built at a cost of ₹2,761.12 crore
  • Malur to Bangarpet (27.1 km) – cost ₹1,496.30 crore
  • Bangarpet to Bethamangala (17.5 km) – cost ₹1,047.63 crore

The only work left in Karnataka is removing a small hill to build a minor bridge.

In reply to a question from Rajya Sabha MP P. Wilson, Gadkari gave updates on the four packages of the project being built in Tamil Nadu.

Although he had earlier hoped the expressway would be ready by December 2024, current progress shows that August 2025 is a more practical date. One section in Andhra Pradesh may be completed by early 2026.

Bengaluru-Chennai Expressway -A Progress Update

Table with 6 columns and 13 rows.
Package (Length)Length(kms)CoverageContractorCompletion%Expected Completion Date
Karnataka Package 126Hoskote to MalurDilip Buildcon99Completed
Karnataka Package 227Malur to BangarpetDilip Buildcon99Completed
Karnataka Package 318Bangarpet to BethamangalaKCC Buildcon99Completed
Andhra Package 125Bethamangala to BaireddypalleMontecarlo6531.03.2025
Andhra Package 231Baireddypalle to BangarupalemAPCO Infratech4517.06.2026
Andhra Package 329Bangarupalem to GudipalaDilip Buildcon8403.10.2024
Tamilnadu Package 124Gudipala to WalajahpetMontecarlo6231.12.2024
Tamilnadu Package 225Walajahpet to ArakkonamKCC Buildcon7830.11.2024
Tamilnadu Package 326Arakkonam to KancheepuramDP Jain & Co.5131.03.2025
Tamilnadu Package 432Kancheepuram to SriperambadurRamalingam Construction6128.02.2025
Total Expressway Length (Main Carriageway)262Hoskote To Sriperumbudur
Six Laning NH4 Sriperumbudur-Maduravoyal23Sriperumbudur-MaduravoyalNHAI9931.08.2024
Maduravoyal-Chennai Port Elevated Expressway20Maduravoyal To Chennai PortJ Kumar Infraprojects120.05.2026

(Source: Swarajyamag)

In Tamil Nadu, a new 106 km greenfield expressway is being built and divided into four parts:

  • Gudipala (Andhra Pradesh) to Walajapet
  • Walajapet to Arakkonam
  • Arakkonam to Kancheepuram
  • Kancheepuram to Sriperumbudur

Work is moving ahead at different speeds. The stretch from Walajapet to Arakkonam is 78% complete, while Arakkonam to Kancheepuram is at 51%.

In Andhra Pradesh, work on three parts was delayed due to the need for environmental approvals.

In March 2023, the National Board for Wildlife gave permission to begin construction near a forest and wildlife area as part of Phase 2 of the project. This phase needed special clearance because the route goes through the Palamaner Reserved Forest, which is near the Kaundinya Wildlife Sanctuary. About 50 km of the road falls inside the eco-sensitive zone (within 10 km of a wildlife sanctuary).

Though the road doesn’t directly go through the sanctuary, it does pass nearby. It also cuts through Palamaner Reserved Forest, part of the Rayala Elephant Reserve. For this, around 54.64 acres of forest land were used.

Phase 2 is 85 km long, mostly in Andhra Pradesh, with a 5.5 km stretch in Karnataka. It starts near N.G. Hulkur village (close to Bangarpet in Kolar, Karnataka) and ends at Ramapuram village in Chittoor, Andhra Pradesh.

Construction work for this phase has been given to Montecarlo Ltd., PCO Infratech Pvt. Ltd., and Dilip Buildcon Ltd.

This part of the expressway will include:

  • 17 major bridges (one over a canal)
  • 34 minor bridges
  • 20 underpasses for vehicles
  • 8 overpasses for vehicles
  • 26 small vehicle underpasses
  • 2 toll plazas
  • 4 interchanges

Since the expressway crosses elephant routes at three spots in the Rayala Elephant Reserve, the NHAI has added special designs like elephant underpasses, culverts, and bridges to allow animals to move freely.

A survey with the Forest Department helped decide where to build these underpasses. To protect small animals too, minor bridges will be built across streams, and three-box culverts will be added for their movement.

The Wildlife Board has made it clear that the forest land taken must only be used for the expressway, not for any business use. All work must be done under the Forest Department’s supervision, with clear markings done before construction starts. Also, digging in nearby forest areas to collect soil is not allowed.

About The Author

Anil Agarwal is a Senior Content Writer at infrainfohub.com. With a passion for Infrastructure, he enjoys crafting engaging and informative content in this field. Anil's expertise lies in writing articles, reviews, and features that captivate readers and keep them informed about the latest trends and news in the Infrastructure sector. His dedication to delivering high-quality content makes her a valuable asset to the team at infrainfohub.com.

Leave a Reply

Your email address will not be published. Required fields are marked *

You May Also Like