Bengaluru-Chennai Expressway Set to Fully Operational by August 2025

Union Road Transport Minister Nitin Gadkari recently announced that the Bengaluru-Chennai Expressway will be inaugurated by Prime Minister Narendra Modi before December this year.

The Karnataka portion of the expressway, spanning 71 km, is nearly finished, whereas substantial work remains in the Andhra and Tamil Nadu segments.

Completed sections include Hoskote to Malur (26.4 km) at a cost of Rs 2,761.12 crore, Malur to Bangarpet (27.1 km) costing Rs 1,496.30 crore, and Bangarpet to Bethamangala (17.5 km) at Rs 1,047.63 crore.

The only remaining task in Karnataka is the removal of a hillock to facilitate the construction of a minor bridge.

Responding to a question posed by Rajya Sabha member P. Wilson, Gadkari provided updates on the completion status of the four packages of the expressway currently underway in Tamil Nadu.

Despite Gadkari’s optimism about the December 2024 inauguration, an analysis of the progress suggests that a realistic timeframe for the completion of all packages is August 2025, with one package in Andhra likely to be operational in early 2026.

Bengaluru-Chennai Expressway -A Progress Update

Table with 6 columns and 13 rows.
Package (Length)Length(kms)CoverageContractorCompletion%Expected Completion Date
Karnataka Package 126Hoskote to MalurDilip Buildcon99Completed
Karnataka Package 227Malur to BangarpetDilip Buildcon99Completed
Karnataka Package 318Bangarpet to BethamangalaKCC Buildcon99Completed
Andhra Package 125Bethamangala to BaireddypalleMontecarlo6531.03.2025
Andhra Package 231Baireddypalle to BangarupalemAPCO Infratech4517.06.2026
Andhra Package 329Bangarupalem to GudipalaDilip Buildcon8403.10.2024
Tamilnadu Package 124Gudipala to WalajahpetMontecarlo6231.12.2024
Tamilnadu Package 225Walajahpet to ArakkonamKCC Buildcon7830.11.2024
Tamilnadu Package 326Arakkonam to KancheepuramDP Jain & Co.5131.03.2025
Tamilnadu Package 432Kancheepuram to SriperambadurRamalingam Construction6128.02.2025
Total Expressway Length (Main Carriageway)262Hoskote To Sriperumbudur
Six Laning NH4 Sriperumbudur-Maduravoyal23Sriperumbudur-MaduravoyalNHAI9931.08.2024
Maduravoyal-Chennai Port Elevated Expressway20Maduravoyal To Chennai PortJ Kumar Infraprojects120.05.2026

(Source: Swarajyamag)

In Tamil Nadu, the greenfield expressway, which covers a distance of 106 km, is divided into four packages: Gudipala (AP) to Walajapet, Walajapet to Arakkonam, Arakkonam to Kancheepuram, and Kancheepuram to Sriperumbudur.

The physical progress varies, with the Walajapet to Arakkonam section at 78% completion, and the Arakkonam to Kancheepuram section at 51%.

In Andhra Pradesh, the work on three packages was delayed due to the need for securing environmental clearances.

In March 2023, the National Board for Wildlife approved the commencement of construction near the forest reserve and wildlife zone area as part of the second phase of the expressway.

The second phase required additional clearance from the Wildlife Board since the proposed alignment passes through the Palamaner Reserved Forest area. Approximately 50 km of this phase falls within the ‘Eco-sensitive Zone’ (defined as an area within a 10 km radius from the outer boundary of a sanctuary) of the Kaundinya Wildlife Sanctuary.

Although the second phase does not pass through any ecological protected areas, the Koundinya Wildlife Sanctuary exists within a 10 km radius of the project alignment.

The project alignment also traverses the Palamaner Reserved Forest Area under the Chittoor Forest Division and forms part of the Rayala Elephant Reserve. Around 54.64 acres of forest reserve area were acquired.

The second phase of the expressway is 85 km long, running mainly through Andhra Pradesh, except for a 5.5 km stretch in Karnataka.

This phase starts near N.G. Hulkur Village, next to Bangarpet in the Kolar district of Karnataka, and ends at Ramapuram Village in Gudipala mandal in the Chittoor district of Andhra Pradesh.

Montecarlo Ltd. (MCL), PCO Infratech Pvt. Ltd., and Dilip Buildcon Ltd. (DBL) have been awarded the construction packages under this phase.

This phase will feature 17 major bridges (including one major canal over the bridge), 34 minor bridges, 20 vehicular underpasses, eight vehicular overpasses, 26 light vehicular underpasses, two toll plazas, and four interchanges.

Part of the Palamaner Reserve Forest constitutes the Rayala Elephant Reserve, with elephant movement routes intersecting the project alignment at three locations.

To avoid habitat fragmentation and disruption due to the proposed expressway, the NHAI has incorporated design measures such as bridges, elephant underpasses, and culverts in the forest stretch.

Based on a survey of elephant movement routes conducted in consultation with the forest department, elephant underpasses have been proposed at three locations.

As additional measures to ensure the free movement of wild animals in the forest area, minor bridges have been proposed across all streams intercepted by the project alignment. Three box culverts have also been proposed to provide access for small-sized wild animals.

The Wildlife Board has mandated that the NHAI ensure the wildlife area is utilized solely for the expressway and not for any commercial purpose.

The Board also stipulated that the diversion work for the project must be carried out under the supervision of the Forest Department, with demarcation of the diversion areas by the agency before commencing work. The agency is prohibited from carrying out excavation work in the surrounding forest land to collect earth.

Anil Agarwal is a Senior Content Writer at infrainfohub.com. With a passion for Infrastructure, he enjoys crafting engaging and informative content in this field. Anil's expertise lies in writing articles, reviews, and features that captivate readers and keep them informed about the latest trends and news in the Infrastructure sector. His dedication to delivering high-quality content makes her a valuable asset to the team at infrainfohub.com.

Leave a Comment