Surat Metro’s TBM Tapi Records Final Breakthrough at Surat Railway Station

Gulermak – Sam India Builtwell JV The final breakthrough of TBM S94 was celebrated at Surat Railway Station on the 22.77 km Line-1 (Sarthana-Dream City) of the Surat Metro Phase 1 project on Wednesday.

This interesting milestone is the sixth and final breakthrough of the 3.46 km CS2/UG1 package connecting Kapodra-Surat Railway Station.

TBM S94 is a Terratech Earth Pressure Balance (EPB) machine, which constructed three tunnels for the up-line at Kapodra in December 2022. Following is a brief description of all three tunnels:

  • Kapodra to Labheshwar Chowk (1.45 km – hidden breakthrough in January 2024)
  • Labheshwar Chowk to Central Warehouse (655m – first visible breakthrough in March 2024)
  • Central Warehouse to Surat Railway Station (389m – second visible breakthrough in September 2024)

This is not the first time this has happened in India, but my general map under the banner of Gulermak-Sam JV, which I use for system contracts, includes this event:

In March 2021, Gujarat Metro Rail Corporation (GMRC) awarded Gulermak-Sam India JV a contract to build the 3.46 km package CS2/UG1.

Six tunnels (three twin tunnels) have been constructed by S78 (Narmada) and S94 (Tapi) and three stations at Kapodara, Labheshwar Chowk and Central Warehouse have been constructed in their area.

In the photos above and below the back-up gantry of TBM S78 (Narmada) can be seen being pulled out for the parallel down-line tunnel.

This changeover marks the end of the work of S94! 2484 m of tunnels and 208 m of tunnel through Labheshwar Chowk station, which will be demolished. In August 2024, its sister machine S78 (TBM Smooth) had completed the construction of all three parallel tunnels for the up-line.

J Kumar Infraprojects has two machines: TBM S25B (Amir) and S28B (Dia). These are building the tunnels from Surat Railway Station to Chowk Bazar from April 2023. I will add updates on their status here as they become available.

Check out more updates on Surat Metro section or my home page! Sign up for instant free email notifications on new posts here. Did you like this article? Support the site here to get updates.

Jay Shah

Jay Shah is a Content Manager at infrainfohub.com, specializing in the realms of ongoing events related to Infrastructure. With a passion for all things Infra-related, Jay dedicates himself to providing insightful and engaging content to his readers. Jay's knack for writing captivating articles makes him an invaluable asset to the team at infrainfohub.com.

Recent Posts

China Successfully Completes Maglev Train Trail Run With 1000 Kph Speed

In a landmark event, China has triumphantly executed a demonstration of its ultra-high-speed (UHS) maglev…

1 day ago

Navi Mumbai International Airport to be fully Operational in March 2025

The Navi Mumbai International Airport (NMIA) will land its first aircraft on a trial basis…

1 day ago

Bengaluru-Chennai Expressway Set to Fully Operational by August 2025

Union Road Transport Minister Nitin Gadkari recently announced that the Bengaluru-Chennai Expressway will be inaugurated…

3 days ago

Delhi Gurgaon Expressway Route, Map, Toll and More

The Delhi Gurgaon Expressway opened in 2008 and became a major transportation threat between Delhi…

3 days ago

Darbhanga Anand Vihar Amrit Bharat Express Ticket Fares, Stations and More

Railway officials said that these trains have aerodynamic engines. Amrit Bharat Express has attractive brown…

3 days ago

Surat Outer Ring Road: Phase 2 Set to Begin After Diwali

The outer ring road being built around Surat was planned to have 27.77 km of…

3 days ago